The acceptance testing for the grid connection and COD (Commercial Operation Date) of the rooftop solar power system at AEON MALL Ha Long, Quang Ninh, took place on November 10, 2026, with the participation of the DATA Cons team and relevant parties. DATA Cons was responsible for the design, supply of materials and equipment, and installation of the 2 MWp system.

What does electrical connection and COD acceptance testing include?
Regarding the electrical connection acceptance item, the DATA Cons team and relevant parties discussed the connection between the solar power system and the building's electrical system. The connection point is where the power from the rooftop system connects to the shopping mall's electrical system.

COD acceptance
On the same day, the parties involved conducted the COD (Commercial Operation Date) acceptance test. The two milestones have different focuses. The connection acceptance test focuses on the electrical connections, while the COD acceptance test is linked to confirming the point at which the system transitions to commercial operation. The image in the technical room shows the inverter and electrical cabinet of the system.

Scope of rooftop solar power at AEON MALL Ha Long
The 2 MWp system consists of solar panels on the roof and electrical equipment for connection to the building. The solar panels collect sunlight to generate direct current (DC) electricity. The inverter converts this electricity into alternating current (AC) for connection to the building's electrical system. On-site photos show two work areas: the solar panel and inverter station on the roof, and the electrical cabinet in the technical room.
See more AEON MALL Ha Long rooftop solar power project to understand the scope of DATA Cons deployment.